Building Fundamental Commissioning
All respective Commissioning Services are lead by an ANSI-ASHRAE Certified Commissioning Process Management Professional, following the most current ASHRAE Guideline 0-2019 — The Commissioning Process which has incorporated and revised as applicable the contents of Guideline 0-2013 — The Commissioning Process; and its preceding version Guideline 0-2013 — The Commissioning Process. This 2019 edition of ASHRAE Guideline 0 updates terminology to reflect an evolving whole-building Commissioning Process (Cx) and harmonizes terminology and its usage with that of ASHRAE/IES Standard 202.
Our Commissioning and documentation protocols as well follow other applicable standards, testing and validation methodologies that are applicable to the work being completed. For instance with Retro Commissioning and Energy Audits we add provisions from the Association of Energy Engineers (AEE) in addition to ASHRAE Level III, Level II and Level I audit protocols. With Envelope and Enclosure our work specifically adheres to the technical requirements of NIBS Guideline 3-2012, Exterior Enclosure Technical Requirements for the Commissioning Process, as they relate to energy, water, indoor environmental quality, and durability. … goto Envelope / Enclosure Commissioning Services for more detailed information.
In our care for our Client’s best interests we additionally in all work effort provide the inclusion of Project Management Institute globally accepted PMI Project, Program and Portfolio Best Management Practices and Processes are implemented. The inclusion of PMI decades certified Project Management Professional assures that Owners Project Requirements are specifically fully articulated as soon as our team is retained and continue to be that barometer and benchmark where goals, waypoints and requirements are measured against for more accurate documentation of project successes.
Over these decades long experience our Principal Daniel A. Huard, LEED Fellow, PMP has had ongoing support within global Building Standards organizations as well as within the Operational Excellence fields. A small sampling of the entities that we have helped the further definition and inclusion of Commissioning include entities like USGBC, GBCI, NSF, National Fenestration Rating Council, US DOE, ASHRAE, AEE, GBI, ILFI, IWBI and numerous others;
Contributed to the validation of value addition with adoption with LAUSD and CEC; contributed with the further qualification of required activities with US Green Building Council’s LEED version 4.1 and LEED version 5.
Our expertise is vast and varied, an example of which is the documentation of $500,000 in Envelope/Enclosure deficiencies in 12 hours of contiguous observations during one client’s site visit. With our multidisciplined professional backgrounds we are known as Global Building Science Authorities known for our giving back to the professions by training other engineers, architects and auditors.
Since we contributed to the development of LEED v4, LEED v4.1 and LEED version 5 we are happy to share the link , content and current requirements for Fundamental Commissioning and Verification | U.S. Green Building Council version 4.1 herein.
Since we contributed to the development of LEED v4, LEED v4.1 and LEED version 5 we are happy to share the link with content and current requirements for Fundamental Commissioning and Verification | U.S. Green Building Council version 4.1 herein.
“Intent
Requirements
Commissioning Process Scope
Complete the following commissioning (Cx) process activities for mechanical, electrical, plumbing, and renewable energy systems and assemblies, in accordance with ASHRAE Guideline 0-2013 and ASHRAE Guideline 1.1–2007 for HVAC&R Systems, as they relate to energy, water, indoor environmental quality, and durability.
- Develop the OPR.
- Develop a BOD.
The commissioning authority (CxA) must do the following:
- Review the OPR, BOD, and project design.
- Develop and implement a Cx plan.
- Confirm incorporation of Cx requirements into the construction documents.
- Develop construction checklists.
- Develop a system test procedure.
- Verify system test execution.
- Maintain an issues and benefits log throughout the Cx process.
- Prepare a final Cx process report.
- Document all findings and recommendations and report directly to the owner throughout the process.
Requirements for exterior enclosures are limited to inclusion in the owner’s project requirements (OPR) and basis of design (BOD), as well as the review of the OPR, BOD and project design. ASTM E2947-16: Standard Guide for Building Enclosure Commissioning provides additional guidance.
The review of the exterior enclosure design may be performed by a qualified independent member of the design or construction team (or an employee of that firm) who is not directly responsible for design of the building enclosure for the project.
Commissioning Authority Qualifications
By the end of the design development phase, engage a commissioning authority with the following qualifications.
- The CxA must have documented commissioning process experience on at least two building projects with a similar scope of work. The experience must extend from early design phase through at least 10 months of occupancy;
- The CxA may be a qualified employee of the owner, an independent consultant, an employee of the design or construction firm who is not part of the project’s design or construction team, or a disinterested subcontractor of the design or construction team.
- For projects smaller than 20,000 square feet (1 860 square meters), the CxA may be a qualified member of the design or construction team.
In all cases, the CxA must report his or her findings directly to the owner.
Current Facilities Requirements and Operations and Maintenance Plan
Prepare and maintain a current facilities requirements and operations and maintenance plan that contains the information necessary to operate the building efficiently. The plan must include the following:
- a sequence of operations for the building;
- the building occupancy schedule;
- equipment run-time schedules;
- setpoints for all HVAC equipment;
- set lighting levels throughout the building;
- minimum outside air requirements;
- any changes in schedules or setpoints for different seasons, days of the week, and times of day;
- a systems narrative describing the mechanical and electrical systems and equipment;
- a preventive maintenance plan for building equipment described in the systems narrative; and
- a commissioning program that includes periodic commissioning requirements, ongoing commissioning tasks, and continuous tasks for critical facilities.”
Please return as we continue to share additional information
Please visit our Service Offerings, Core Services & Capabilities portions of our website to learn more.
Contact us Today and as well give us the opportunity to work with you and you will find why we have so many satisfied and return clients.
Copyright ©1998-2024 D.A. Huard, Copyright ©2007-2024 Humann Building Solutions, LLC.