Building Enhanced Commissioning

Humann Building Solutions has been a long term premium provider of Building Enhanced Commissioning for LEED and other project types. Our team follows processes acknowledged by ASHRAE and as well other Green Building Rating Systems requirements globally.

Typically Building Enhanced Commissioning brings additional rigor to the Commissioning process and thus as well brings a greater level of assurance to the owner and more complete alignment with Owners Project Requirements as well. 

 

These services are an extension to the conventional Fundamental Commissioning and as well within the LEED Green Building Certification Ratings Systems may gain additional credits towards LEED Certification. 

We share the following Enhanced Commissioning information extracted from LEED BD+C New Construction version 4.1 Enhanced Commissioning | U.S. Green Building Council << we share this link for the most current and accurate information available related to LEED Enhanced Commissioning. 

We also note that beyond LEED Certification Building Envelope/Enclosure Commissioning as well as Monitoring Based Commissioning are additional services often provided by specialty providers like Humann Building Solutions, LLC. We have those options delineated seperately as well.

“LEED BD+C: New Constructionv4.1 – LEED v4.1

Enhanced Commissioning

Energy and Atmosphere

Possible 6 Points

Intent

To further support the design, construction, and eventual operation of a project that meets the owner’s project requirements for energy, water, indoor environmental quality, and durability.

Requirements

Implement, or have in place a contract to implement, the following commissioning process activities in addition to those required under EA Prerequisite Fundamental Commissioning and Verification. Commissioning Authority Qualifications:

The CxA must have documented commissioning process experience on at least two building projects with a similar scope of work. The experience must extend from early design phase through at least 10 months of occupancy;

The CxA may be a qualified employee of the owner, an independent consultant, an employee of the design or construction firm who is not part of the project’s design or construction team, or a disinterested subcontractor of the design or construction team.

Option 1. Enhanced Systems Commissioning (3-4 points)
Path 1: Enhanced Commissioning (3 points)

Complete the following commissioning process (Cx) activities for mechanical, electrical, plumbing, and renewable energy systems and assemblies in accordance with ASHRAE Guideline 0–2013 and ASHRAE Guideline 1.1–2007 for HVAC&R systems, as they relate to energy, water, indoor environmental quality, and durability. The commissioning authority must do the following:

  • Review contractor submittals.

  • Verify inclusion of systems manual requirements in construction documents.

  • Verify inclusion of operator and occupant training requirements in construction documents.

  • Verify systems manual updates and delivery.

  • Verify operator and occupant training delivery and effectiveness.

  • Verify seasonal testing.

  • Review building operations 10 months after substantial completion.

  • Develop an on-going commissioning plan.

Include all enhanced commissioning tasks in the OPR and BOD.


OR

Path 2: Enhanced and Monitoring-Based Commissioning (4 points)

Achieve Path 1.
AND
Develop monitoring-based procedures and identify points to be measured and evaluated to assess performance of energy- and water-consuming systems. Include the procedures and measurement points in the commissioning plan. Address the following:

  • roles and responsibilities;

  • measurement requirements (meters, points, metering systems, data access);

  • the points to be tracked, with frequency and duration for trend monitoring;

  • the limits of acceptable values for tracked points and metered values (where appropriate, predictive algorithms may be used to compare ideal values with actual values);

  • the elements used to evaluate performance, including conflict between systems, out-of-sequence operation of systems components, and energy and water usage profiles;

  • an action plan for identifying and correcting operational errors and deficiencies;

  • training to prevent errors;

  • planning for repairs needed to maintain performance; and

  • the frequency of analyses in the first year of occupancy (at least quarterly).

Update the systems manual with any modifications or new settings, and give the reason for any modifications from the original design.


AND/OR

Option 2. Building Enclosure Commissioning (2 points)

Fulfill the requirements in EA Prerequisite Fundamental Commissioning and Verification as they apply to the building’s enclosure in addition to mechanical and electrical systems and assemblies.

Complete the following commissioning process (Cx) activities for the building’s thermal envelope in accordance with ASHRAE Guideline 0–2013 and ASTM E2947-16: Standard Guide for Building Enclosure Commissioning, as they relate to energy, air and water tightness, indoor environmental quality, and durability.

The qualified independent member of the design or construction team responsible for building enclosure commissioning must complete the following:

  • Review contractor submittals.

  • Verify inclusion of systems manual requirements in construction documents for enclosure systems.

  • For specialty enclosure systems with controls and automation:

    • Verify inclusion of operator and occupant training requirements in construction documents.

    • Verify systems manual updates and delivery.

    • Verify operator and occupant training delivery and effectiveness.

    • Verify seasonal testing.

    • Review building operations 10 months after substantial completion.

  • Develop an on-going enclosure commissioning plan for maintenance, renewal and revitalization cycles. “

The preceding information provided within the quotes in maroon color is Copyright 2024 US Green Building Council, Green Building Certification Institute.